This document describes the interactions of smart community infrastructures (interactions between multiple infrastructures, between infrastructures and stakeholders, and between infrastructures and the external environment). It describes the framework (a set of processes and methodologies) for these interactions to ensure the consistency of smart community infrastructures is well identified and managed. There are two potential use cases for this document. The first is for the green field site, where all the smart community infrastructures can be designed and developed at the same time. This is of value to planners and investors of major new infrastructure developments. The second is for the brown field site and builds on the first and will support efficient management of an existing urban area by taking into account the increasing interdependencies of the infrastructures on each other and the way they should be managed as a system of systems. This document will also take into account accelerating technological and environmental changes. Since this framework aims to ensure the consistency among different systems consisting of smart community infrastructures, the scope of this document does not overlap with any existing works that are developed or being developed at the existing TCs addressing issues at individual infrastructure level. NOTE This document describes a management case (not a management system), i.e. specific processes that an organization needs to follow in order to meet specific objectives of this document.
Cadre pour l’intégration et l’exploitation des infrastructures communautaires intelligentes — Partie 2: Approche holistique et stratégie pour le développement, le fonctionnement et la maintenance des infrastructures communautaires intelligentes
General Information
Standards Content (Sample)
INTERNATIONAL ISO
STANDARD 37155-2
First edition
2021-05
Framework for integration and
operation of smart community
infrastructures —
Part 2:
Holistic approach and the strategy
for development, operation and
maintenance of smart community
infrastructures
Cadre pour l’intégration et l’exploitation des infrastructures
communautaires intelligentes —
Partie 2: Approche holistique et stratégie pour le développement,
le fonctionnement et la maintenance des infrastructures
communautaires intelligentes
Reference number
©
ISO 2021
© ISO 2021
All rights reserved. Unless otherwise specified, or required in the context of its implementation, no part of this publication may
be reproduced or utilized otherwise in any form or by any means, electronic or mechanical, including photocopying, or posting
on the internet or an intranet, without prior written permission. Permission can be requested from either ISO at the address
below or ISO’s member body in the country of the requester.
ISO copyright office
CP 401 • Ch. de Blandonnet 8
CH-1214 Vernier, Geneva
Phone: +41 22 749 01 11
Email: copyright@iso.org
Website: www.iso.org
Published in Switzerland
ii © ISO 2021 – All rights reserved
Contents Page
Foreword .v
Introduction .vi
1 Scope . 1
2 Normative references . 1
3 Terms and definitions . 1
4 Understanding of smart community infrastructure layers . 4
4.1 Smart community infrastructure system layer . 4
4.2 Smart community infrastructure layer . 4
4.3 Smart community sub-infrastructure layer . 4
5 Benefits of applying this document . 4
5.1 General . 4
5.2 General benefits . 5
5.3 Benefits for community authorities . 5
5.4 Benefits for investors or lenders . 5
5.5 Benefits for developers, operators and infrastructure owners . 5
5.6 Benefits for service providers . 6
5.7 Benefits for people in smart communities . 6
6 Life cycle phases of smart community infrastructure . 7
6.1 General . 7
6.2 Initiation (phase 1) . 7
6.2.1 Smart community concept (phase 1-1). 7
6.3 Design of target infrastructures (phase 2) . 8
6.3.1 Basic concept (phase 2-1) . 8
6.3.2 Basic plan (phase 2-2) . . 9
6.3.3 Fundamental design (phase 2-3) .10
6.3.4 Tendering (phase 2-4) . .10
6.3.5 Implementation design (phase 2-5) .11
6.4 Construction and assessment (phase 3) .11
6.4.1 Manufacturing, construction, and installation (phase 3-1) .11
6.4.2 Individual and combination tests and validation (phase 3-2) .11
6.4.3 Overall assessment of smart community infrastructures as a whole
(phase 3-3) .12
6.5 Operation and maintenance (phase 4) .13
6.6 Redevelopment and rehabilitation (phase 5).13
6.7 Decommissioning (phase 6) .14
7 General process to ensure consistency .14
7.1 General .14
7.2 Process overview .14
7.3 Action items in V process (item 2 in Figure) .15
7.3.1 Item 1: Setting the targets for infrastructures .15
7.3.2 Item 2: Analyse the solutions for different infrastructures to achieve the
targets .15
7.3.3 Item 3: Validation and Verification .15
7.3.4 Item 4: Monitoring the performance of infrastructures .15
7.3.5 Item 5: Improve the targets .15
8 Guidelines for ensuring consistency .15
8.1 General .15
8.2 Smart community concept (phase 1-1) .15
8.2.1 Recommendations for verification and validation .15
8.2.2 Responsibility .16
8.3 Basic concept (phase 2-1) .16
8.3.1 Recommendations for verification .16
8.3.2 Recommendations for validation .16
8.3.3 Responsibility .16
8.4 Basic plan (phase 2-2) .16
8.4.1 Recommendations for verification .16
8.4.2 Recommendations for validation .17
8.4.3 Responsibility .17
8.5 Fundamental design (phase 2-3) .17
8.5.1 Recommendations for verification .17
8.5.2 Recommendations for validation .17
8.5.3 Responsibility .17
8.6 Tendering (phase 2-4) .17
8.6.1 Recommendations for verification .17
8.6.2 Responsibility .18
8.7 Implementation design (phase 2-5) .18
8.7.1 Recommendations for verification .18
8.7.2 Recommendations for validation .18
8.7.3 Responsibility .19
8.8 Manufacturing, construction and installation (phase 3-1) .19
8.9 Individual and combination tests and validation (phase 3-2) .19
8.10 Overall assessment and validation (phase 3-3) .19
8.11 Operation and maintenance (phase 4) .19
8.11.1 Recommendations for verification .19
8.11.2 Recommendations for validation .19
8.11.3 Responsibility .20
8.12 Redevelopment and rehabilitation (phase 5).20
8.12.1 Recommendations for verification and validation .20
8.12.2 Responsibility .20
8.13 Decommissioning (phase 6) .
...